The City of Sanibel has provided an important update, announcing that the repaving of Periwinkle Way commenced today, October 23.
The project focuses on the section of Periwinkle Way extending from approximately 500 feet west of Casa Ybel Road to about one-third of a mile east of Donax Street. To minimize disruption, all milling and paving operations will occur during evening and overnight hours, with nighttime lane closures in effect between 9 p.m. and 6 a.m.
Project Paving Schedule
The city’s contractor has released the following detailed paving schedule, which is subject to change based on weather conditions:
| Date | Work Description |
| Oct. 23 | Resetting a manhole in the westbound lane of Periwinkle just west of Dixie Beach Boulevard. |
| Oct. 26 | Paving turnouts on side streets of the westbound lane of Periwinkle from Periwinkle Park to just west of Jerry’s Foods (including Whisperwood Way, Main Street, Fitzhugh Street, Palm Street, and Dixie Beach). |
| Oct. 27 | Paving turnouts on side streets of the eastbound lane of Periwinkle from just west of Jerry’s to Periwinkle Park (including Casa Ybel Road and Donax Street). |
| Oct. 28 | Paving the westbound lane of Periwinkle from Periwinkle Park to the Dixie Beach intersection. |
| Oct. 29 | Paving both westbound and eastbound lanes of Periwinkle from Dixie Beach to just west of Jerry’s. |
| Oct. 30 | Paving the eastbound lane from Dixie Beach to Periwinkle Park. |
The City assures the public that access to all residences and businesses will be maintained at all times throughout the project. Drivers are reminded to operate their vehicles slowly and cautiously through the work zones when crews are present. The contractor will utilize clear signage and flaggers to efficiently direct traffic.
For more detailed information regarding the project, citizens may contact the Public Works Department at sanpw@mysanibel.com or call 239-472-6397.